Programme Update: January 2019

 

In December, the development made one of the two drainage connections into the public sewer. The school’s internal works continue to proceed with floor laying in progress. The tower’s façade has been completed, whilst internal works to form the new apartments continue on the floors below. The Nile Street block’s cladding works have progressed enough, to…

Continue reading

Programme Update: December 2018

 

In November the site has switched over to the project’s permanent substation. The school’s internal works continue to progress well with ceiling installation underway, walls receiving their first coat of paint and the finished doors to the classrooms being installed. The tower’s cladding panel install has reached Level 28, whilst internal works to form the…

Continue reading

Programme Update: November 2018

 

In October, the school has been preparing for its new ceilings to be installed. The Sports Hall has received its first coat of paint and the tower’s roof waterproofing works have been completed, as the remaining three levels of cladding are installed. Internal works on the floors below have continued, with some of the apartments…

Continue reading

Programme Update: October 2018

 

In September the site has removed one of its tower cranes and the protective screens to the tower have been completely removed. The tower’s cladding and internal works have progressed, with ceiling installation and flooring works both starting. The school’s roof photovoltaic (PV) panel installation has commenced.  These panels capture the sun’s energy and convert…

Continue reading

Programme Update: September 2018

 

In August, internal works to the school has continued. The tower’s concrete frame works have been completed and removal of the protective screens has commenced. Window and glazing works have commenced on the Nile Street Block, enabling internal works to start on Level 01. During September, the project will swap onto permanent electricity supply. This…

Continue reading

Programme update: August 2018

 

In July, works to the school’s internals have continued with the ground slab being screeded ready for the new floor finishes. The tower’s core has been completed and the formwork used to give the concrete is shape has been removed. The concrete floor slabs have reached Level 26. The tower’s cladding installation is progressing well…

Continue reading

Programme Update: July 2018

 

In June the school classrooms have been built and the new mechanical and electrical services have been installed. The glazing is nearly complete, making the building watertight. Cladding is complete to level 12 of the tower, whilst the concrete core is complete to level 27 and the concrete slabs are complete to level 22. The…

Continue reading

Important Update: Extended working hours to increase height of tower crane

 

We would like to take the opportunity to give you advance warning that the New Regent’s College project has been granted permission by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 16th June 8am – 8pm Sunday 17th June 9am – 8pm The…

Continue reading

Programme Update: June 2018

 

During May works to the school have continued with the window frame and glazing in progress to create weather tight internal areas for the school’s fit-out. The school’s internal classroom walls are being built with the new mechanical and electrical services being installed. The pre-cast concrete facade is in progress to the Nile Street block…

Continue reading