In December, the development made one of the two drainage connections into the public sewer. The school’s internal works continue to proceed with floor laying in progress. The tower’s façade has been completed, whilst internal works to form the new apartments continue on the floors below. The Nile Street block’s cladding works have progressed enough, to…
In November the site has switched over to the project’s permanent substation. The school’s internal works continue to progress well with ceiling installation underway, walls receiving their first coat of paint and the finished doors to the classrooms being installed. The tower’s cladding panel install has reached Level 28, whilst internal works to form the…
In October, the school has been preparing for its new ceilings to be installed. The Sports Hall has received its first coat of paint and the tower’s roof waterproofing works have been completed, as the remaining three levels of cladding are installed. Internal works on the floors below have continued, with some of the apartments…
In September the site has removed one of its tower cranes and the protective screens to the tower have been completely removed. The tower’s cladding and internal works have progressed, with ceiling installation and flooring works both starting. The school’s roof photovoltaic (PV) panel installation has commenced. These panels capture the sun’s energy and convert…
In August, internal works to the school has continued. The tower’s concrete frame works have been completed and removal of the protective screens has commenced. Window and glazing works have commenced on the Nile Street Block, enabling internal works to start on Level 01. During September, the project will swap onto permanent electricity supply. This…
We would like to take the opportunity to give you advance warning that the New Regent’s College project will temporarily extend its working hours on the following dates and times: Saturday 1st September 8am – 8pm Sunday 2nd September 9am – 8pm The reason for the extended opening of the site over the weekend is to permit…
In July, works to the school’s internals have continued with the ground slab being screeded ready for the new floor finishes. The tower’s core has been completed and the formwork used to give the concrete is shape has been removed. The concrete floor slabs have reached Level 26. The tower’s cladding installation is progressing well…
In June the school classrooms have been built and the new mechanical and electrical services have been installed. The glazing is nearly complete, making the building watertight. Cladding is complete to level 12 of the tower, whilst the concrete core is complete to level 27 and the concrete slabs are complete to level 22. The…
We would like to take the opportunity to give you advance warning that the New Regent’s College project has been granted permission by the London Borough of Hackney’s Environmental Health Department to temporarily extend the site’s working hours on the following dates and times: Saturday 16th June 8am – 8pm Sunday 17th June 9am – 8pm The…
During May works to the school have continued with the window frame and glazing in progress to create weather tight internal areas for the school’s fit-out. The school’s internal classroom walls are being built with the new mechanical and electrical services being installed. The pre-cast concrete facade is in progress to the Nile Street block…
We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By clicking “Accept All”, you consent to the use of ALL the cookies. However, you may visit "Cookie Settings" to provide a controlled consent.
This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.