Programme Update: February 2017

 

Works during February 2017 During February, our demolition contractor has left site and our ground works contractor has been working hard to prepare the site ready for piling to commence in March. Pile probing has been completed to ensure there is no obstructions where the new foundation piles will be installed. We have removed a…

Continue reading

Programme Update: January 2017

 

Works during January 2017 During January, our demolition programme was slightly delayed due to us encountering asbestos within the existing school’s slab. Our licensed contractor successfully removed the asbestos, allowing the demolition to school’s foundations to continue. The sewer amendment works within Britannia Walk have now been completed and both the footway and highway reopened…

Continue reading

Programme Update: December 2016

 

To Date Works commenced on site on 28th November 2016. There will be various phases to the project, with final completion of the project in Autumn 2019. Works during December 2016 Early December saw the site cleared of vegetation ready for construction works to begin. Demolition of the unoccupied existing structures and features on the…

Continue reading

First Programme Update: November 2016

 

We are pleased to be working in partnership with Hackney Council and the Local Education Partnership as principal contractor for the redevelopment of the New Regent’s College site. The project is part of Hackney Council’s wider schools building programme, to ensure there are enough school places for local children. Their borough- wide programme will see…